Monday, June 29, 2009
Dedication Day!
Wednesday, June 24, 2009
Pictures!!!
Tuesday, June 23, 2009
House - Check!
- Roof = Done
- Plumbing = Done
- Electrical = Done
- Insulation = Done
- Drywall = Done
- Taping and Mudding = Done
- Siding = Done
- Brickwork on the Front = Done
- Front Porch = Being Done Today
- Painting = Being Done Today
Monday, June 15, 2009
Raising the Roof
Saturday, June 13, 2009
Ballroom Blitz!!!
So as I sit here, high as a kite on pain meds, my wife just got home from the build today. I'm super disappointed that I wasn't able to be there today, and even more disappointed that i'll probably be out of commission for the whole build.
Thursday, June 4, 2009
Personal Setback
So every day, i'm getting more and more excited to get working on this build!! I have the countdown going until the blitz build starts, i'm ready to take pictures every day of everything thats been done, getting geared up to write up a blog entry every night about the days fun and exciting steps along this journy...
Saturday, May 30, 2009
Roof - Pre-Raise
St. Claire College in Windsor did all the prefab for the walls and roof. Not exactly sure why they're doing the roof first, but hey, i'm not a contractor! :)
Tuesday, May 26, 2009
Subfloors - CHECK
was scheduled to work on Sunday at the build site, I was very excited to get going on the build as I haven’t yet done anything with the house. Sure enough, I get a call on Saturday night, saying “no need to come on Sunday, they got everything done”
I was definitely looking forward to going to the build site, but at the same time, how could you not be excited that there is progress on your new home?!
Here’s what is going to happen during the blitz build… it takes place from June 13th to June 27th.
- Raising Exterior Walls
- Building Floors
- Raising the Roof (whoop whoop)
- Plumbing
- Electrical
- Dry Walling
- Painting
- Flooring
- Trim Work
- Kitchen Cabinets
- Siding
- Bricking
Sunday, May 3, 2009
We Have A Basement!
Tuesday, April 28, 2009
Scene Setting
Our build is going to be fast and furious. From what I’ve seen online about other builds they could last up to a year to be completely built. The timeframe for our house, is 12 weeks from ground break to move in.
How ridiculous is that?!?
I’m one of those people that doesn’t get excited about something until it happens. For the last month or so, we’ve been going to our meetings and sessions about finances, and being good neighbours and house maintenance etc.. but it still didn’t feel real. After our last session, we decided to take a trip to the build site, and saw that they had the hole dug… it STARTED to hit me… I got a little excited and actually started to believe this is happening. We found out that they’re pouring foundation as of yesterday and today, which is a week ahead of schedule. Getting a little more excited now. J
Well it’s my first blog, and I think it’s too long, but I’m setting the stage right? I’ll try give updates every few days – and once the blitz build starts on June 20th, I’ll probably update every night.